We always suggest to build
the driveway at the same time
we are building the pad for
many reasons: |
|
|
| |
•
The trucks are bringing
the same materials anyway.
• The trucks rolling
in and out compacts
the dirt.
• The dozer and
equipment
is already set up on
site and there is no
extra mobilization costs.
• Most of the time
when it is to wet to
get the trucks to the
pad
area we need to literally
build the road
with select fill to
get them in. It takes
more dirt but if time
is of the essence there
is no other choice.
• We place
select fill (sandy/clay)
on the ground, spread
it, and roll it to get
compaction.
We suggest for the select
fill to be at least
5"- 6" thick.
• Options
of crushed material:
crushed concrete,
crushed limestone, crushed
asphalt, or crushed
granite. |
|
|
|
| After
doing this you can at a later
time lay asphalt or pour concrete
on top.
|
|